» Go to news mainCampus Construction Update
Posted by Stephanie Rogers on
June 23, 2017
in
News
- Truck traffic will continue down through farm road as indicated on plan submitted.
- Shoring will commence shortly and noise in the area is expected.
- The relocation of underground communications will be happening over the next couple of weeks. Further notice will be given at a later time. It should be noted that an outage will occur affecting IT and possible other departments.
- Hot work activities ongoing in the existing plant
- Major deliveries expected over next 2 weeks would include cable tray system
Recent News
- Longstanding Partnership Recognized with Provincial Award
- Welcome to Extended Learning Program Assistants
- WUSC Refugee Student Fund
- New faces on campus
- Dal AC Queer Faculty and Staff Caucus meet‑up ‑ July 8.
- The Value of the Detour: How Jess MacQueen found her path through university
- A life in Agriculture, a future in innovation: Meet Jill Lockerby
- Excellence in Action: Annual awards celebrate impact across the Agricultural Campus