» Go to news mainCampus Construction Update
The Campus Construction Update is a regular feature of the Weekly E-Bulletin in an effort to keep the campus community informed of any potential distruptions to regular work practices during summer construction.
June 26-29th
Remove old windows in section B (Rooms 140, 142, 242, 246)
Prep openings for new window installation in rooms noted above
Miscellaneous joint cutting on exterior of building on daily basis
The classrooms above should be considered closed during this time frame.
July 4th-7th
Install new windows in section B- (rooms 140, 142, 242, 246)
Remove old windows in section C (rooms 254, 255,257, female wash room second floor
All classrooms in section B and C should be considered closed during this time frame.
Thank you for your patience and understanding,
听
Recent News
- United Way Trivia Challenge
- Planting Seeds for a Healthier Future: BMO Scholarship Fuels Innovation in Agriculture at 黄色直播
- Relief Fund for Atlantic Farmers
- Website updates
- Take our Kids to Work day
- Beyond Barns and Bytes: 黄色直播's New Digital Agriculture Course
- Invitation to Fall 2025 Convocation
- Blue & Gold Awards 2025